SMSTS mock test 2026: free practice questions
Revise for the Site Management Safety Training Scheme with 25 questions drawn from our 150-question bank. Free, unofficial practice with explanations and an optional 35-minute timer.
Untimed practice · 0/25 answered
Question 1 of 25
Original, unofficial questions. Nothing is saved: leaving or refreshing this page clears this attempt. Timed mode shows explanations after you finish. Two-answer questions need both correct choices for any marks.
What is the current SMSTS test format?
CITB’s February 2026 scheme rules specify 25 questions in 35 minutes: 18 multiple-choice questions worth one mark each, plus seven multi-response or short written questions worth two marks each. The examination pass mark is 26 out of 32.
Our practice uses 18 single-answer and seven choose-two questions. It does not reproduce the written-answer assessment or CITB’s marking process. Both correct choices and no extra choice are needed for two practice marks. Untimed practice draws across all topics; timed mocks focus the two-mark questions on height, vehicles, handling, asbestos, dust, noise and vibration.
The official assessment permits the GE700 or XA6 publication during its final 15 minutes. Follow your trainer’s current instructions. Our practice has no reference-material restriction.
The real course also requires attendance, exercises and a satisfactory trainer review. Completing this practice does not award a qualification or replace the course.
Which topics can I revise?
Questions cover risk assessment, welfare, worker consultation, fire, first aid, hazardous substances, work equipment, site transport, temporary works and environmental controls. Work at height, asbestos, dust, noise, vibration and manual handling appear in both course banks.
The management questions also cover client and principal contractor duties, construction phase planning, excavations and rescue planning. There are 25 role-specific questions and 125 shared safety questions in each bank.
HSE legal references apply to Great Britain. Environmental questions marked “England” use the English rules. For work in Northern Ireland, check HSENI and the applicable regulations. Short revision questions cannot replace site-specific risk assessment or competent advice.
Choose the right revision
These courses are separate from the CITB Health, Safety and Environment test used in card applications. Compare SMSTS and SSSTS, or use the CSCS operatives mock test. You can also try our SSSTS supervisor practice.
Ten sample questions and answers
These questions are available without JavaScript. Open each answer for its explanation and source.
1. Under CDM 2015, which dutyholder appoints the principal contractor on a project involving more than one contractor?
- The project client
- The lead architect
- The design manager
- The safety adviser
Answer: The project client.
Why: The client appoints the principal contractor to control the construction phase.
Client appoints; principal contractor coordinates.
Official source for sample 12. When must the written construction phase plan be prepared?
- Before construction work starts
- After the first site inspection
- During the first working week
- Once all subcontractors arrive
Answer: Before construction work starts.
Why: The plan must be ready before the construction phase begins and kept up to date.
Plan first; review as work changes.
Official source for sample 23. Who needs a site-specific induction before starting work?
- Only workers without a site card
- All workers starting on the site
- Only newly qualified site workers
- Only workers using powered tools
Answer: All workers starting on the site.
Why: A card or experience does not replace an induction explaining this site’s arrangements.
Every worker; this site.
Official source for sample 34. When must suitable welfare facilities be available?
- Once the main structure is ready
- After the first working week ends
- From the start of site work
- Once the largest trade team arrives
Answer: From the start of site work.
Why: Welfare must be provided from the start and maintained throughout construction.
Welfare starts with the work.
Official source for sample 45. At what employee headcount must an employer record significant risk-assessment findings?
- At least 3 employees
- At least 5 employees
- At least 10 employees
- At least 20 employees
Answer: At least 5 employees.
Why: Employers with five or more employees must record significant findings. Smaller employers must still assess and control risk.
Five triggers recording, not the duty to assess.
Official source for sample 56. New equipment changes the risks of a task. What should happen to the risk assessment?
- Keep it until the annual review
- Wait for an accident to occur
- Review the affected controls
- Leave the review to the supplier
Answer: Review the affected controls.
Why: Changed equipment can create new risks, so check the controls and update the assessment.
Change the work; review the controls.
Official source for sample 67. Choose TWO considerations when selecting access equipment for work at height.
- The task and duration of the work
- The ground and working conditions
- The cheapest option regardless of risk
- The worker's preference without assessment
Answer: The task and duration of the work; The ground and working conditions.
Why: Equipment must suit the assessed task and conditions, rather than price or convenience alone.
Official source for sample 78. Choose TWO features of sensible work-at-height planning.
- Plan how emergencies will be handled
- Rely on luck during very short tasks
- Leave rescue decisions until after a fall
- Prevent falls where reasonably practicable
Answer: Plan how emergencies will be handled; Prevent falls where reasonably practicable.
Why: Prevention and emergency arrangements belong in the plan before work begins.
Official source for sample 89. Choose TWO measures that help drivers and pedestrians use a site safely.
- Let pedestrians choose any convenient route
- Assume every driver sees behind the vehicle
- Provide clear, suitable routes and crossings
- Give relevant site information to visitors
Answer: Provide clear, suitable routes and crossings; Give relevant site information to visitors.
Why: Layout and information work together; neither depends on perfect driver visibility.
Official source for sample 910. Choose TWO things to assess before vehicle loading or unloading.
- Whether rushing will reduce the waiting queue
- The stability of the load and vehicle
- The safety of the surrounding work area
- Whether pedestrian barriers can be ignored
Answer: The stability of the load and vehicle; The safety of the surrounding work area.
Why: Loading creates risks from movement, instability and contact with other people.
Official source for sample 10Common questions
Is this the official SMSTS test?
No. UK Trade Jobs wrote these original practice questions from public safety guidance. CITB has not provided or endorsed them. Your score does not predict an exam result or prove site competence.
How many questions are in this SMSTS mock test?
Each new attempt draws 25 questions from a bank of 150. There are 32 practice marks. Shared safety topics also appear in our other course bank; the two banks contain 175 different questions in total.
What is the SMSTS pass mark?
CITB's current scheme rules give 26 out of 32 as the official examination pass mark. Course attendance, exercises and the trainer review also matter. We show a practice score, not a pass certificate.
Can I practise without an account?
Yes. No account, email address or payment is needed. Your answers stay in this browser session and are cleared if you leave or refresh the page. Ten sample questions and answers below also work without JavaScript.
Sources and version
Source review by the UK Trade Jobs editorial team. How we research and review.
Format checked against CITB’s current SMSTS scheme rules (PDF) on 11 November 2026. See the official scheme-rules index for updates.
Bank version: smsts-practice-2026-11-11-v2. Each question links to its safety source. UK Trade Jobs is independent of CITB.